Assessment Year | 2005 |
---|---|
Principal Product | Protein Hydrolysates |
NAICS | 311514: Dry, Condensed, and Evaporated Dairy Product Manufacturing |
SIC | 2023: Dry, Condensed, and Evaporated Dairy Products |
Sales Range | $50 M to 100M |
# of Employees | 115 |
Plant Area |
60,126
ft2
|
Annual Production | 11,023
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $367,601 | 7,814,700 |
kWh
|
$0.047 |
Electricity Demand | $90,936 | 15,156 |
kW-mo/yr
|
$6.00 |
Electricity Fees | $(-3,938.0) | - |
|
- |
Fuel Oil #4 | $871,767 | 118,615 |
MMBtu
|
$7.35 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $227,668 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $79,643 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #4 Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1232: Keep boiler tubes clean | $17,434 | - | - | - |
$17,434
-
MMBtu
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,497 | - |
$2,981
63,422
kWh
|
$516
-
kW-mo/yr
|
- | - | |
03 | 2.4314: Use synthetic lubricant | $488 | - |
$416
8,848
kWh
|
$72
-
kW-mo/yr
|
- | - | |
04 | 2.1222: Install turbulators | $24,498 | $512 | - | - |
$24,498
-
MMBtu
|
- | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $47,114 | $10,000 | - | - |
$47,114
-
MMBtu
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,882 | $765 |
$3,306
70,342
kWh
|
$576
-
kW-mo/yr
|
- | - | |
07 | 2.2113: Repair or replace steam traps | $8,034 | $2,780 | - | - |
$8,034
-
MMBtu
|
- | |
08 | 2.4221: Install compressor air intakes in coolest locations | $2,271 | $667 |
$1,935
41,172
kWh
|
$336
-
kW-mo/yr
|
- | - | |
09 | 3.6192: Use a less expensive method of waste removal | $119,913 | $75,924 |
$48,441
1,030,656
kWh
|
$12,672
-
kW-mo/yr
|
- | $58,800 | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $420 | $408 |
$81
1,717
kWh
|
$12
-
kW-mo/yr
|
- | $327 | |
11 | 2.6211: Conserve energy by efficient use of vending machines | $117 | $343 |
$99
2,102
kWh
|
$18
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $227,668 | $91,399 |
$57,259
1,218,259
kWh
|
$14,202
-
kW-mo/yr
|
$97,080
-
MMBtu
|
$59,127 | ||
TOTAL IMPLEMENTED | $79,643 | $14,620 |
$5,738
122,079
kWh
|
$996
-
kW-mo/yr
|
$72,582
-
MMBtu
|
$327 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #4 Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs