ITAC Assessment: DS0129
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Pharmaceuticals
NAICS
n/a
SIC 2830:
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 60,000
ft2
Annual Production 22,230,000
pieces
Production Hrs. Annual 4,550
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,796 1,362,544
kWh
Electricity Demand $29,557 4,200
kW-mo/yr
Electricity Fees $1,788 -
Natural Gas $9,009 1,802
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,877 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,728

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,030 $6,676 $2,594
76,202
kWh
$1,436
-
kW-mo/yr
- - -
02 2.4221: Install compressor air intakes in coolest locations $192 $300 $124
3,517
kWh
$68
-
kW-mo/yr
- - -
03 3.5315: Lease / purchase baler; sell cardboard to recycler $1,555 $4,750 - - $1,555
-
lb
- -
04 2.8121: Apply for tax-free status for energy purchases $372 $360 - - - - $372
05 4.446: Automate finishing process $1,728 $4,900 - - - $1,728 -
TOTAL RECOMMENDED $7,877 $16,986 $2,718
79,719
kWh
$1,504
-
kW-mo/yr
$1,555
-
lb
$1,728 $372
TOTAL IMPLEMENTED $1,728 $4,900 - - - $1,728 -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs