Assessment Year | 1997 |
---|---|
Principal Product | Food Processing Equipment |
NAICS |
n/a
|
SIC | 3556: Food Products Machinery |
Sales Range | $10 M to 50M |
# of Employees | 126 |
Plant Area |
120,000
ft2
|
Annual Production | 16
pieces
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $73,230 | 2,256,741 |
kWh
|
$0.032 |
Electricity Demand | $41,557 | 5,508 |
kW-mo/yr
|
$7.54 |
Electricity Fees | $2,402 | - |
|
- |
Natural Gas | $21,361 | 3,597 |
MMBtu
|
$5.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,500 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,526 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $389 | $750 |
$253
7,913
kWh
|
$136
-
kW-mo/yr
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,032 | $135 |
$670
21,102
kWh
|
$362
-
kW-mo/yr
|
- | - | - | |
03 | 2.6232: Install set-back timers | $7,453 | $4,500 |
$3,460
108,148
kWh
|
- |
$3,993
-
MMBtu
|
- | - | |
04 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,231 | $700 | - | - | - |
$1,231
-
Tgal
|
- | |
05 | 4.211: Consider use / purchase of bulk materials where possible | $5,810 | $3,267 | - | - | - | - | $5,810 | |
06 | 4.211: Consider use / purchase of bulk materials where possible | $3,585 | $6,840 | - | - | - | - | $3,585 | |
TOTAL RECOMMENDED | $19,500 | $16,192 |
$4,383
137,163
kWh
|
$498
-
kW-mo/yr
|
$3,993
-
MMBtu
|
$1,231
-
Tgal
|
$9,395 | ||
TOTAL IMPLEMENTED | $15,526 | $8,602 |
$4,130
129,250
kWh
|
$362
-
kW-mo/yr
|
$3,993
-
MMBtu
|
$1,231
-
Tgal
|
$5,810 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs