ITAC Assessment: DL0257
ITAC logo
ITAC Assessment: DL0257
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product semiconductor-based electronic parts
NAICS 334413: Semiconductor and Related Device Manufacturing
SIC 3674: Semiconductors and Related Devices
Sales Range $1
M
to 5
M
# of Employees 135
Plant Area 27,000
ft2
Annual Production 10,000
units
Production Hrs. Annual 2,500
hrs
Location (State) Delaware

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $121,383 871,360
kWh
Electricity Demand $12,471 1,453
kW-mo/yr
Electricity Fees $2,806 -
Natural Gas $4,469 504
MMBtu
Other Gas $1,417 1
MMBtu
TOTAL YEARLY COSTS $142,546
RECOMMENDED SAVINGS* $64,346 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.9114: Use solar heat to make electricty $58,383 $470,000 $53,049
381,650
kWh
$5,334
-
kW-mo/yr
-
02 2.7224: Reduce space conditioning during non-working hours $4,000 - $4,000
26,149
kWh
- -
03 2.6231: Utilize controls to operate equipment only when needed $343 - $311
2,235
kWh
$32
-
kW-mo/yr
-
04 2.2211: Use optimum temperature $1,329 - - - $1,329
-
MMBtu
05 2.7261: Install timers and/or thermostats $291 $131 $122
878
kWh
- $169
-
MMBtu
TOTAL RECOMMENDED $64,346 $470,131 $57,482
410,912
kWh
$5,366
-
kW-mo/yr
$1,498
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs