| Assessment Year | 2024 |
|---|---|
| Principal Product | flight simulators and high-value projection displays |
| NAICS | 336411: Aircraft Manufacturing |
| SIC | 3721: Aircraft |
| Sales Range | $10 M to 50M |
| # of Employees | 400 |
| Plant Area |
150,000
ft2
|
| Annual Production | 100
units
|
| Production Hrs. Annual | 2,860
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $340,580 | 4,203,330 |
kWh
|
$0.081 | |
| Electricity Demand | $64,903 | 8,590 |
kW-mo/yr
|
$7.56 | |
| Electricity Fees | $1,462 | - |
|
- | |
| Natural Gas | $23,078 | 2,574 |
MMBtu
|
$8.97 | |
| Waste Disposal Costs | |||||
| Water Usage | $3,931 | 414 |
Tgal
|
$9.50 | |
| TOTAL YEARLY COSTS | $433,954 | ||||
| RECOMMENDED SAVINGS* | $34,343 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $18,350 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.6231: Utilize controls to operate equipment only when needed | $12,043 | - |
$12,043
148,674
kWh
|
|
| 02 | 2.6231: Utilize controls to operate equipment only when needed | $4,258 | - |
$4,258
52,566
kWh
|
|
| 03 | 2.7224: Reduce space conditioning during non-working hours | $11,703 | - |
$11,703
144,486
kWh
|
|
| 04 | 2.6242: Minimize operation of equipment maintained in standby condition | $4,290 | $11,200 |
$4,290
52,968
kWh
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,049 | $191 |
$2,049
21,339
kWh
|
|
| TOTAL RECOMMENDED | $34,343 | $11,391 |
$34,343
420,033
kWh
|
||
| TOTAL IMPLEMENTED | $18,350 | $191 |
$18,350
222,579
kWh
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs