ITAC Assessment: LE0519
ITAC logo
ITAC Assessment: LE0519
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Hardwood Boards
NAICS 321113: Sawmills
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 12
Plant Area 200,000
ft2
Annual Production 15,000,000
units
Production Hrs. Annual 4,160
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $232,820 4,956,791
kWh
Electricity Demand $106,874 16,875
kW-mo/yr
Electricity Fees $56,998 -
TOTAL YEARLY COSTS $396,692
RECOMMENDED SAVINGS* $71,390 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,994

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $971 $25 $508
10,796
kWh
$463
-
kW-mo/yr
02 2.4221: Install compressor air intakes in coolest locations $1,106 $1,000 $479
10,189
kWh
$627
-
kW-mo/yr
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $48,358 $85,000 $32,298
687,189
kWh
$16,060
-
kW-mo/yr
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $835 $1,670 $613
13,034
kWh
$222
-
kW-mo/yr
05 2.7142: Utilize higher efficiency lamps and/or ballasts $6,082 $16,800 $4,379
93,184
kWh
$1,703
-
kW-mo/yr
06 2.1311: Replace electrically-operated equipment with fossil fuel equipment $14,038 $57,000 $11,259
239,558
kWh
$2,779
-
kW-mo/yr
TOTAL RECOMMENDED $71,390 $161,495 $49,536
1,053,950
kWh
$21,854
-
kW-mo/yr
TOTAL IMPLEMENTED $8,994 $19,495 $5,979
127,203
kWh
$3,015
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs