| Assessment Year | 2024 |
|---|---|
| Principal Product | Precision machined metal parts |
| NAICS | 333249: Other Industrial Machinery Manufacturing |
| SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 16 |
| Plant Area |
13,500
ft2
|
| Annual Production | 800,000
units
|
| Production Hrs. Annual | 4,600
hrs
|
| Location (State) | Delaware |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $63,036 | 483,893 |
kWh
|
$0.13 | |
| Electricity Demand | $4,869 | 1,257 |
kW-mo/yr
|
$3.87 | |
| Electricity Fees | $792 | - |
|
- | |
| Natural Gas | $7,000 | 700 |
MMBtu
|
$10.00 | |
| Waste Disposal Costs | |||||
| Water Usage | $1,157 | 77 |
Tgal
|
$15.05 | |
| TOTAL YEARLY COSTS | $76,854 | ||||
| RECOMMENDED SAVINGS* | $10,150 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $2,249 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6231: Utilize controls to operate equipment only when needed | $265 | - |
$265
1,893
kWh
|
- | |
| 02 | 2.2211: Use optimum temperature | $516 | - |
$241
1,718
kWh
|
$275
-
MMBtu
|
|
| 03 | 2.2211: Use optimum temperature | $769 | $1,439 | - |
$769
-
MMBtu
|
|
| 04 | 2.4224: Upgrade controls on compressors | $7,260 | $30,000 |
$7,260
51,859
kWh
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $699 | $319 |
$699
4,995
kWh
|
- | |
| 06 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $641 | $2,820 | - |
$641
-
MMBtu
|
|
| TOTAL RECOMMENDED | $10,150 | $34,578 |
$8,465
60,465
kWh
|
$1,685
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $2,249 | $1,758 |
$1,205
8,606
kWh
|
$1,044
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs