ITAC Assessment: WI0364
ITAC logo
ITAC Assessment: WI0364
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Heat Treating, Metal Finishing, Specialty Coatings
NAICS
n/a
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $10
M
to 50
M
# of Employees 135
Plant Area 105,750
ft2
Annual Production 82,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $227,958 6,756,741
kWh
Electricity Demand $175,133 12,472
kW-mo/yr
Electricity Fees $29,715 -
Natural Gas $426,871 161,146
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,074 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,162

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 3.6192: Use a less expensive method of waste removal $20,162 - - - - $20,162
-
lb
02 2.3132: Recharge batteries on during off-peak demand periods $7,614 $15,000 - $7,614
-
kW-mo/yr
- -
03 2.2621: Modify refrigeration system to operate at a lower pressure $6,918 $20,750 $4,624
130,715
kWh
$2,294
-
kW-mo/yr
- -
04 2.4221: Install compressor air intakes in coolest locations $1,730 $740 $1,235
34,877
kWh
$495
-
kW-mo/yr
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $489 $90 $339
9,672
kWh
$150
-
kW-mo/yr
- -
06 2.2511: Insulate bare equipment $1,567 $3,871 - - $1,567
-
MMBtu
-
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $594 $438 $346
9,672
kWh
$248
-
kW-mo/yr
- -
TOTAL RECOMMENDED $39,074 $40,889 $6,544
184,936
kWh
$10,801
-
kW-mo/yr
$1,567
-
MMBtu
$20,162
-
lb
TOTAL IMPLEMENTED $20,162 - - - - $20,162
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs