Assessment Year | 2015 |
---|---|
Principal Product | Large Mining Trucks |
NAICS | 333131: Mining Machinery and Equipment Manufacturing |
SIC | 3532: Mining Machinery and Equipment, Except Oil and Gas Field Machinery and Equipment |
Sales Range | greater than $500 M |
# of Employees | 442 |
Plant Area |
909,807
ft2
|
Annual Production | 450
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $668,774 | 14,162,325 |
kWh
|
$0.047 |
Electricity Demand | $81,269 | 32,036 |
kW-mo/yr
|
$2.54 |
Electricity Fees | $13,176 | - |
|
- |
Natural Gas | $722,723 | 118,233 |
MMBtu
|
$6.11 |
LPG | $32,358 | 1,385 |
MMBtu
|
$23.36 |
Fuel Oil #2 | $92,857 | 3,704 |
MMBtu
|
$25.07 |
Other Gas | $5,687 | 338 |
MMBtu
|
$16.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $370,013 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $54,415 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7231: Use radiant heater for spot heating | $140,934 | $105,000 | - | - |
$140,934
-
MMBtu
|
- | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $19,322 | $13,700 |
$16,726
354,364
kWh
|
$2,596
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,997 | $40,950 |
$12,463
264,057
kWh
|
$1,935
-
kW-mo/yr
|
- | $347 | - | $252 | |
04 | 2.7261: Install timers and/or thermostats | $11,689 | $17,188 |
$11,689
247,655
kWh
|
- | - | - | - | - | |
05 | 2.3132: Recharge batteries on during off-peak demand periods | $7,295 | $25 | - |
$7,295
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7135: Install occupancy sensors | $6,580 | $2,250 |
$4,876
103,297
kWh
|
$1,704
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4314: Use synthetic lubricant | $4,742 | $300 |
$4,104
86,956
kWh
|
$638
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $2,994 | $900 |
$2,592
54,912
kWh
|
$402
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,388 | $25 |
$2,067
43,790
kWh
|
$321
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $845 | $2,500 |
$732
15,516
kWh
|
$113
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $839 | $725 |
$392
8,322
kWh
|
$29
-
kW-mo/yr
|
- | $168 | - | $250 | |
12 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $157,388 | $8,500 | - | - | - | - | $157,388 | - | |
TOTAL RECOMMENDED | $370,013 | $192,063 |
$55,641
1,178,869
kWh
|
$15,033
-
kW-mo/yr
|
$140,934
-
MMBtu
|
$515 | $157,388 | $502 | ||
TOTAL IMPLEMENTED | $54,415 | $58,575 |
$39,116
828,742
kWh
|
$14,282
-
kW-mo/yr
|
- | $515 | - | $502 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs