Assessment Year | 2021 |
---|---|
Principal Product | Bottled Beverages |
NAICS | 312111: Soft Drink Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $100 M to 500M |
# of Employees | 106 |
Plant Area |
133,000
ft2
|
Annual Production | 65,500
Tgal
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $628,556 | 13,458,137 |
kWh
|
$0.047 | |
Electricity Demand | $215,645 | 35,184 |
kW-mo/yr
|
$6.13 | |
Electricity Fees | $8,954 | - |
|
- | |
Natural Gas | $133,878 | 35,892 |
MMBtu
|
$3.73 | |
Waste Disposal Costs | |||||
Water Usage | $760,948 | 122,919 |
Tgal
|
$6.19 | |
TOTAL YEARLY COSTS | $1,747,981 | ||||
RECOMMENDED SAVINGS* | $299,705 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $76,388 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.4154: Eliminate leaks in water lines and valves | $900 | - | - |
$280
-
MMBtu
|
$620
-
Tgal
|
- | |
02 | 3.4155: Meter waste water | $172,100 | $3,000 | - | - | - |
$172,100
-
Tgal
|
|
03 | 3.4114: Replace city water with recycled water via cooling tower | $23,050 | $9,490 | - | - |
$23,050
-
Tgal
|
- | |
04 | 2.4322: Use or replace with energy efficient substitutes | $860 | $81,000 |
$860
13,700
kWh
|
- | - | - | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $8,798 | $1,000 |
$8,798
139,651
kWh
|
- | - | - | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,987 | $20,000 | - |
$1,987
-
MMBtu
|
- | - | |
07 | 2.2441: Preheat boiler makeup water with waste process heat | $1,320 | $8,000 | - |
$1,320
-
MMBtu
|
- | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $19,340 | $48,750 |
$19,340
307,000
kWh
|
- | - | - | |
09 | 2.2437: Recover waste heat from equipment | $7,620 | $7,000 |
$780
12,450
kWh
|
$6,840
-
MMBtu
|
- | - | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,490 | $25,000 |
$17,490
277,600
kWh
|
- | - | - | |
11 | 2.4226: Use / purchase optimum sized compressor | $3,150 | $4,600 |
$3,150
50,000
kWh
|
- | - | - | |
12 | 2.4226: Use / purchase optimum sized compressor | $25,290 | $57,350 |
$25,290
401,400
kWh
|
- | - | - | |
13 | 2.2437: Recover waste heat from equipment | $6,000 | $5,500 | - |
$6,000
-
MMBtu
|
- | - | |
14 | 2.1221: Replace obsolete burners with more efficient ones | $11,800 | $9,120 | - |
$11,800
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $299,705 | $279,810 |
$75,708
1,201,801
kWh
|
$28,227
-
MMBtu
|
$23,670
-
Tgal
|
$172,100
-
Tgal
|
||
TOTAL IMPLEMENTED | $76,388 | $173,840 |
$52,438
832,351
kWh
|
$280
-
MMBtu
|
$23,670
-
Tgal
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs