| Assessment Year | 2017 |
|---|---|
| Principal Product | RF and Microwave Technology |
| NAICS | 334413: Semiconductor and Related Device Manufacturing |
| SIC | 3674: Semiconductors and Related Devices |
| Sales Range | $100 M to 500M |
| # of Employees | 300 |
| Plant Area |
100,000
ft2
|
| Annual Production | 5,000,000
units
|
| Production Hrs. Annual | 4,806
hrs
|
| Location (State) | Maryland |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $261,147 | 3,541,902 |
kWh
|
$0.074 | |
| Electricity Demand | $50,243 | 7,538 |
kW-mo/yr
|
$6.67 | |
| Electricity Fees | $40,330 | - |
|
- | |
| Natural Gas | $5,413 | 382 |
MMBtu
|
$14.17 | |
| Waste Disposal Costs | |||||
| Water Usage | $13,323 | 1,234,000 |
Tgal
|
$0.011 | |
| TOTAL YEARLY COSTS | $370,456 | ||||
| RECOMMENDED SAVINGS* | $60,855 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $44,591 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4224: Upgrade controls on compressors | $20,880 | - |
$20,880
282,000
kWh
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,435 | $15,000 |
$4,435
50,400
kWh
|
- | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,100 | $9,375 |
$5,100
58,000
kWh
|
- | |
| 04 | 2.4131: Size electric motors for peak operating efficiency | $1,676 | $1,375 |
$1,676
19,049
kWh
|
- | |
| 05 | 2.2437: Recover waste heat from equipment | $2,364 | $654 |
$1,032
11,728
kWh
|
$1,332
-
MMBtu
|
|
| 06 | 2.4321: Upgrade obsolete equipment | $17,600 | $5,950 |
$17,600
200,000
kWh
|
- | |
| 07 | 2.6231: Utilize controls to operate equipment only when needed | $8,800 | $3,940 |
$8,800
100,000
kWh
|
- | |
| TOTAL RECOMMENDED | $60,855 | $36,294 |
$59,523
721,177
kWh
|
$1,332
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $44,591 | $22,325 |
$44,591
551,449
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs