ITAC Assessment: DL0166
ITAC logo
ITAC Assessment: DL0166
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Mechanical Power Transmission
NAICS 336211: Motor Vehicle Body Manufacturing
SIC 3713: Truck and Bus Bodies
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 9,999
ft2
Annual Production 40,000
units
Production Hrs. Annual 8,760
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $117,295 846,578
kWh
Electricity Demand $20,119 3,030
kW-mo/yr
Electricity Fees $4,465 -
Natural Gas $29,476 3,686
MMBtu
TOTAL YEARLY COSTS $171,355
RECOMMENDED SAVINGS* $40,843 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,095

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2437: Recover waste heat from equipment $1,095 $1,036 - - $1,095
-
MMBtu
02 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air $4,815 $27,020 $(-630.0)
(-3,910)
kWh
$(-70.0)
-
kW-mo/yr
$5,515
-
MMBtu
03 2.2531: Re-size charging openings or add movable cover or door $3,496 $9,820 - - $3,496
-
MMBtu
04 2.7231: Use radiant heater for spot heating $1,310 $2,990 - - $1,310
-
MMBtu
05 2.7264: Interlock heating and air conditioning systems to prevent simultaneous operation $18,930 $4,739 $14,354
103,266
kWh
$1,673
-
kW-mo/yr
$2,903
-
MMBtu
06 2.7131: Add area lighting switches $1,520 $910 $1,490
10,740
kWh
$30
-
kW-mo/yr
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $5,810 $35,710 $5,750
41,360
kWh
$60
-
kW-mo/yr
-
08 2.7135: Install occupancy sensors $2,400 $3,900 $2,400
17,273
kWh
- -
09 2.4224: Upgrade controls on compressors $1,467 $565 $1,467
10,559
kWh
- -
TOTAL RECOMMENDED $40,843 $86,690 $24,831
179,288
kWh
$1,693
-
kW-mo/yr
$14,319
-
MMBtu
TOTAL IMPLEMENTED $1,095 $1,036 - - $1,095
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs