| Assessment Year | 2015 |
|---|---|
| Principal Product | Pickles/Peppers/Sauces |
| NAICS | 311941: Mayonnaise, Dressing, and Other Prepared Sauce Manufacturing |
| SIC | 2035: Pickled Fruits and Vegetables, Vegetable Sauces and Seasonings, and Salad Dressings |
| Sales Range | $50 M to 100M |
| # of Employees | 100 |
| Plant Area |
200,000
ft2
|
| Annual Production | 4,000,000
pieces
|
| Production Hrs. Annual | 5,600
hrs
|
| Location (State) | Maryland |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $380,327 | 4,756,144 |
kWh
|
$0.080 |
| Electricity Demand | $90,237 | 11,297 |
kW-mo/yr
|
$7.99 |
| Electricity Fees | $10,197 | - |
|
- |
| Natural Gas | $305,447 | 39,504 |
MMBtu
|
$7.73 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $221,550 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2112: Use correct size steam traps | $12,870 | $2,380 | - | - |
$12,870
-
MMBtu
|
- | |
| 02 | 3.7222: Minimize overflows by installing level controls | $37,680 | $12,400 | - | - |
$24,970
-
MMBtu
|
$12,710
-
Tgal
|
|
| 03 | 2.6231: Utilize controls to operate equipment only when needed | $60,250 | $20,000 |
$52,980
662,210
kWh
|
$7,270
-
kW-mo/yr
|
- | - | |
| 04 | 2.1212: Operate boilers on high fire setting | $10,860 | $4,610 | - | - |
$10,860
-
MMBtu
|
- | |
| 05 | 2.4224: Upgrade controls on compressors | $7,730 | $11,520 |
$5,800
72,510
kWh
|
$1,930
-
kW-mo/yr
|
- | - | |
| 06 | 2.4239: Eliminate or reduce compressed air usage | $9,550 | $14,400 |
$9,100
113,710
kWh
|
$450
-
kW-mo/yr
|
- | - | |
| 07 | 2.2694: Use highest temperature for chilling or cold storage | $1,970 | $4,480 |
$1,720
21,560
kWh
|
$250
-
kW-mo/yr
|
- | - | |
| 08 | 3.4151: Minimize water usage | $80,640 | $200,250 |
$(-5,280.0)
(-66,000)
kWh
|
$(-1,150.0)
-
kW-mo/yr
|
- |
$87,070
-
Tgal
|
|
| TOTAL RECOMMENDED | $221,550 | $270,040 |
$64,320
803,990
kWh
|
$8,750
-
kW-mo/yr
|
$48,700
-
MMBtu
|
$99,780
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs