ITAC Assessment: DL0110
ITAC logo
ITAC Assessment: DL0110
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product conveyors and accumulation tables
NAICS 333922: Conveyor and Conveying Equipment Manufacturing
SIC 3535: Conveyors and Conveying Equipment
Sales Range $1
M
to 5
M
# of Employees 65
Plant Area 55,000
ft2
Annual Production 10
units
Production Hrs. Annual 4,680
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $76,847 660,080
kWh
Electricity Demand $16,064 2,615
kW-mo/yr
Fuel Oil #2 $68,179 2,578
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $35,185 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,320

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #2 Savings
01 2.7491: Insulate glazing, walls, ceilings, and roofs $7,313 $39,750 - $7,313
-
MMBtu
02 2.7261: Install timers and/or thermostats $6,320 $260 - $6,320
-
MMBtu
03 2.4224: Upgrade controls on compressors $10,321 $35,000 $10,321
73,204
kWh
-
04 2.7314: Reduce ventilation air $4,577 $102 - $4,577
-
MMBtu
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,720 $24,800 $2,720
19,300
kWh
-
06 2.2437: Recover waste heat from equipment $1,991 $152 - $1,991
-
MMBtu
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,943 $644 $128
910
kWh
$1,815
-
MMBtu
TOTAL RECOMMENDED $35,185 $100,708 $13,169
93,414
kWh
$22,016
-
MMBtu
TOTAL IMPLEMENTED $6,320 $260 - $6,320
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #2 Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs