Assessment Year | 2012 |
---|---|
Principal Product | Resilient Floors, Tile, Vinyl |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3996: Linoleum, Asphalted-Felt-Base, and Other Hard Surface Floor Coverings, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 650 |
Plant Area |
1,000,000
ft2
|
Annual Production | 288,000
thousand feet
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $3,671,949 | 42,596,959 |
kWh
|
$0.086 |
Natural Gas | $3,245,332 | 327,739 |
MMBtu
|
$9.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,154,724 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $825,960 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.6125: Keep equipment clean | $378,860 | $370,000 |
$138,290
1,608,000
kWh
|
$240,570
-
MMBtu
|
|
02 | 2.1113: Reduce combustion air flow to optimum | $145,934 | $700 |
$75,644
879,580
kWh
|
$70,290
-
MMBtu
|
|
03 | 2.7231: Use radiant heater for spot heating | $410,000 | $1,200,000 | - |
$410,000
-
MMBtu
|
|
04 | 2.4322: Use or replace with energy efficient substitutes | $20,000 | $78,000 |
$20,000
232,500
kWh
|
- | |
05 | 2.7313: Recycle air for heating, ventilation and air conditioning | $11,900 | $14,000 | - |
$11,900
-
MMBtu
|
|
06 | 2.7313: Recycle air for heating, ventilation and air conditioning | $17,900 | $54,500 |
$9,000
105,000
kWh
|
$8,900
-
MMBtu
|
|
07 | 2.7262: Separate controls of air handlers from ac/ heating systems | $7,000 | $20,000 |
$7,000
81,370
kWh
|
- | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,200 | $5,400 |
$5,200
60,650
kWh
|
- | |
09 | 2.4239: Eliminate or reduce compressed air usage | $79,600 | $29,600 |
$79,600
926,000
kWh
|
- | |
10 | 2.4224: Upgrade controls on compressors | $18,230 | $71,500 |
$18,230
212,000
kWh
|
- | |
11 | 2.4224: Upgrade controls on compressors | $60,100 | $101,500 |
$60,100
698,800
kWh
|
- | |
TOTAL RECOMMENDED | $1,154,724 | $1,945,200 |
$413,064
4,803,900
kWh
|
$741,660
-
MMBtu
|
||
TOTAL IMPLEMENTED | $825,960 | $1,667,400 |
$163,490
1,901,150
kWh
|
$662,470
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs