ITAC Assessment: DL0063
ITAC logo
ITAC Assessment: DL0063
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Canned clams, chowders and broths.
NAICS 311710: Seafood Product Preparation and Packaging
SIC 2091: Canned and Cured Fish and Seafoods
Sales Range $10
M
to 50
M
# of Employees 103
Plant Area 78,000
ft2
Annual Production 3,271,000
pieces
Production Hrs. Annual 2,080
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $516,568 3,716,200
kWh
LPG $534,200 39,075
MMBtu
Fuel Oil #2 $167,698 11,254
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $304,641 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $214,332

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings Fuel Oil #2 Savings
01 2.6218: Turn off equipment when not in use $35,600 $100 $35,600
256,000
kWh
- -
02 2.7314: Reduce ventilation air $34,080 $500 - $26,446
-
MMBtu
$7,634
-
MMBtu
03 2.2121: Increase amount of condensate returned $31,600 $1,610 - $24,522
-
MMBtu
$7,078
-
MMBtu
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $33,400 $57,000 $33,400
240,000
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $31,900 $166,850 $31,900
229,498
kWh
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $22,000 $3,000 $22,000
158,400
kWh
- -
07 2.2414: Use waste heat from hot flue gases to preheat $18,958 $60,000 - $14,711
-
MMBtu
$4,247
-
MMBtu
08 2.6218: Turn off equipment when not in use $12,220 $100 - $9,483
-
MMBtu
$2,737
-
MMBtu
09 2.2162: Reduce excess steam bleeding $14,034 $419 - $10,890
-
MMBtu
$3,144
-
MMBtu
10 2.6218: Turn off equipment when not in use $16,180 $1,000 $16,180
116,380
kWh
- -
11 2.7135: Install occupancy sensors $12,978 $1,012 $12,978
93,370
kWh
- -
12 2.2136: Install / repair insulation on steam lines $11,600 $1,585 - $9,002
-
MMBtu
$2,598
-
MMBtu
13 2.2437: Recover waste heat from equipment $10,700 $3,900 - $8,303
-
MMBtu
$2,397
-
MMBtu
14 2.2443: Re-use or recycle hot or cold process exhaust air $7,338 $19,300 - $5,694
-
MMBtu
$1,644
-
MMBtu
15 2.2153: Close off unneeded steam lines $3,627 $400 - $2,815
-
MMBtu
$812
-
MMBtu
16 2.4221: Install compressor air intakes in coolest locations $3,700 $2,100 $3,700
26,400
kWh
- -
17 2.2511: Insulate bare equipment $3,993 $30,400 - $3,099
-
MMBtu
$894
-
MMBtu
18 2.6231: Utilize controls to operate equipment only when needed $733 $615 $733
5,280
kWh
- -
TOTAL RECOMMENDED $304,641 $349,891 $156,491
1,125,328
kWh
$114,965
-
MMBtu
$33,185
-
MMBtu
TOTAL IMPLEMENTED $214,332 $177,091 $119,391
858,928
kWh
$73,675
-
MMBtu
$21,266
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings LPG Savings Fuel Oil #2 Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs