| Assessment Year | 2020 |
|---|---|
| Principal Product | metal parts |
| NAICS | 333519: Rolling Mill and Other Metalworking Machinery Manufacturing |
| SIC | 3549: Metalworking Machinery, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
90,000
ft2
|
| Annual Production | 100,000
units
|
| Production Hrs. Annual | 5,876
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $150,211 | 1,576,400 |
kWh
|
$0.095 | |
| Electricity Fees | $24,889 | - |
|
- | |
| Natural Gas | $82,842 | 30,842 |
MMBtu
|
$2.69 | |
| Waste Disposal Costs | |||||
| Water Usage | $1,354 | 5,141,500 |
Tgal
|
$0.000 | |
| TOTAL YEARLY COSTS | $259,297 | ||||
| RECOMMENDED SAVINGS* | $860,797 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $845,991 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,912 | $330 |
$5,912
62,234
kWh
|
- | - | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,658 | $100 |
$1,658
17,447
kWh
|
- | - | - | - | |
| 03 | 2.4226: Use / purchase optimum sized compressor | $2,643 | $848 |
$2,643
27,820
kWh
|
- | - | - | - | |
| 04 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $1,678 | $800 |
$1,678
17,663
kWh
|
- | - | - | - | |
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,268 | $3,429 | - | $(-650.3) |
$2,918
-
MMBtu
|
- | - | |
| 06 | 3.4113: Treat and reuse rinse waters | $15,861 | $10,000 | - | - | - | $15,861 | - | |
| 07 | 2.7232: Replace existing hvac unit with high efficiency model | $3,966 | $800 | - | - |
$3,966
-
MMBtu
|
- | - | |
| 08 | 2.7291: Reschedule and rearrange multiple-source heating systems | $7,871 | $14,588 |
$4,158
43,772
kWh
|
- |
$3,713
-
MMBtu
|
- | - | |
| 09 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $51,045 | $2,000 | - | - | - | - | $51,045 | |
| 10 | 3.2176: Increase use of automation | $749,435 | $60,000 | - | - | - | - | $749,435 | |
| 11 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,024 | $6,471 |
$(-439.4)
(-4,625)
kWh
|
- |
$2,464
-
MMBtu
|
- | - | |
| 12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $342 | - |
$342
3,595
kWh
|
- | - | - | - | |
| 13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,095 | $16,500 |
$16,095
169,417
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $860,797 | $115,865 |
$32,046
337,324
kWh
|
$(-650.3) |
$13,061
-
MMBtu
|
$15,861 | $800,480 | ||
| TOTAL IMPLEMENTED | $845,991 | $90,530 |
$25,684
270,357
kWh
|
- |
$3,966
-
MMBtu
|
$15,861 | $800,480 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs