ITAC Assessment: UD0668
ITAC logo
ITAC Assessment: UD0668
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Aircraft propellers
NAICS 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 2378:
Sales Range $50
M
to 100
M
# of Employees 296
Plant Area 191,000
ft2
Annual Production 3,600
units
Production Hrs. Annual 8,400
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $191,903 6,501,072
kWh
Electricity Demand $115,803 708
kW-mo/yr
Electricity Fees $23,162 -
Natural Gas $66,594 56,857
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $146,909 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
01 2.8118: Check for accuracy of utility / power meters $48,976 - - - - - - - - $48,976 -
02 4.424: Improve space comfort conditioning $40,000 $44,000 - - - - - - - - $40,000
03 2.7142: Utilize higher efficiency lamps and/or ballasts $22,018 $37,750 $16,354
495,600
kWh
$5,664
-
kW-mo/yr
- - - - - - -
04 2.7131: Add area lighting switches $11,320 $7,350 $11,320
343,013
kWh
- - - - - - - -
05 3.4111: Use closed cycle process to minimize waste water production $4,612 $1,000 - - - $4,612
-
Tgal
- - - - -
06 2.6218: Turn off equipment when not in use $3,423 $200 $3,423
103,740
kWh
- - - - - - - -
07 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown $3,380 - - - $3,380
-
MMBtu
- - - - - -
08 2.7491: Insulate glazing, walls, ceilings, and roofs $2,834 $1,382 - - $2,834
-
MMBtu
- - - - - -
09 3.8136: Switch to a solvent that can be cleaned and re-used $2,248 $7,000 - - - - $7,248
-
gal
- $(-5,000.0) - -
10 2.2437: Recover waste heat from equipment $1,723 $2,000 - - $1,723
-
MMBtu
- - - - - -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $1,224 $2,747 $909
27,552
kWh
$315
-
kW-mo/yr
- - - - - - -
12 2.6218: Turn off equipment when not in use $730 - $730
22,050
kWh
- - - - - - - -
13 2.2136: Install / repair insulation on steam lines $610 $642 $360
10,920
kWh
$250
-
kW-mo/yr
- - - - - - -
14 2.6218: Turn off equipment when not in use $3,071 - $1,771
53,664
kWh
- - - - $1,300 - - -
15 2.7122: Disconnect ballasts $260 $60 $195
5,880
kWh
$65
-
kW-mo/yr
- - - - - - -
16 2.2514: Cover open tanks $253 $200 $59
1,787
kWh
$38
-
kW-mo/yr
$156
-
MMBtu
- - - - - -
17 2.4111: Utilize energy-efficient belts and other improved mechanisms $227 $45 $143
4,340
kWh
$84
-
kW-mo/yr
- - - - - - -
TOTAL RECOMMENDED $146,909 $104,376 $35,264
1,068,546
kWh
$6,416
-
kW-mo/yr
$8,093
-
MMBtu
$4,612
-
Tgal
$7,248
-
gal
$1,300 $(-5,000.0) $48,976 $40,000
TOTAL IMPLEMENTED - - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs