ITAC Assessment: AS0126
ITAC logo
ITAC Assessment: AS0126
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Plastic Bags
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 79
Plant Area 68,000
ft2
Annual Production 6,000,000
lb
Production Hrs. Annual 8,520
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $217,723 2,746,483
kWh
Natural Gas $5,168 801
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $51,652 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $8,176 $11,059 n/a $8,176
103,165
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,339 $5,515 n/a $2,339
27,550
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $325 $30 n/a $325
4,103
kWh
04 2.4133: Use most efficient type of electric motors $13,760 $7,722 n/a $13,760
173,505
kWh
05 2.4314: Use synthetic lubricant $2,409 $968 n/a $2,409
15,533
kWh
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,527 $350 n/a $1,527
19,343
kWh
07 2.2511: Insulate bare equipment $2,152 $705 n/a $2,152
27,257
kWh
08 2.2511: Insulate bare equipment $795 $420 n/a $795
9,965
kWh
09 2.2614: Use cooling tower or economizer to replace chiller cooling $2,003 $7,500 n/a $2,003
25,205
kWh
10 2.8114: Change rate schedules or other changes in utility service $18,166 $25,250 n/a $18,166
-
kWh
TOTAL RECOMMENDED $51,652 $59,519 $51,652
405,626
kWh
TOTAL IMPLEMENTED - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs