Assessment Year | 1996 |
---|---|
Principal Product | injection molded plastic parts |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 42 |
Plant Area |
58,875
ft2
|
Annual Production | 10,165,113
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $64,408 | 2,116,061 |
kWh
|
$0.030 |
Electricity Demand | $49,860 | 5,511 |
kW-mo/yr
|
$9.05 |
Electricity Fees | $2 | - |
|
- |
Natural Gas | $6,385 | 1,712 |
MMBtu
|
$3.73 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,164 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,254 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,430 | $15,373 |
$2,747
83,236
kWh
|
$1,683
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 4.652: Replace existing equipment with more suitable substitutes | $4,590 | $630 | - | - | - | - | - | - | $4,590 | |
03 | 3.8132: Use less toxic and volatile solvent substitutes | $1,940 | $1,790 | - | - | - |
$2,250
-
gal
|
- | $(-310.0) | - | |
04 | 2.2612: Use cooling tower water instead of refrigeration | $1,770 | $3,010 |
$1,770
58,324
kWh
|
- | - | - | - | - | - | |
05 | 3.6192: Use a less expensive method of waste removal | $500 | - | - | - | - | - |
$500
-
lb
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $360 | $160 |
$230
7,327
kWh
|
$130
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $330 | $150 |
$210
6,741
kWh
|
$120
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.4133: Use most efficient type of electric motors | $44 | $58 |
$28
879
kWh
|
$16
-
kW-mo/yr
|
- | - | - | - | - | |
09 | 2.7261: Install timers and/or thermostats | $200 | $160 |
$100
3,224
kWh
|
- |
$100
-
MMBtu
|
- | - | - | - | |
TOTAL RECOMMENDED | $14,164 | $21,331 |
$5,085
159,731
kWh
|
$1,949
-
kW-mo/yr
|
$100
-
MMBtu
|
$2,250
-
gal
|
$500
-
lb
|
$(-310.0) | $4,590 | ||
TOTAL IMPLEMENTED | $10,254 | $16,371 |
$3,215
98,183
kWh
|
$1,949
-
kW-mo/yr
|
- | - |
$500
-
lb
|
- | $4,590 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs