| Assessment Year | 2006 |
|---|---|
| Principal Product | Corrugated Cardboard Boxes |
| NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
150,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $394,838 | 4,967,500 |
kWh
|
$0.079 |
| Electricity Demand | $77,008 | 12,792 |
kW-mo/yr
|
$6.02 |
| Natural Gas | $333,080 | 52,193 |
MMBtu
|
$6.38 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $412,440 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $121,625 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $140,853 | $660,000 |
$295,776
3,744,000
kWh
|
$43,344
-
kW-mo/yr
|
- |
$(-198,267.0)
-
MMBtu
|
- | |
| 02 | 4.122: Develop standard procedures to improve internal yields | $128,263 | $120,000 |
$9,811
124,188
kWh
|
$1,926
-
kW-mo/yr
|
- |
$8,326
-
MMBtu
|
$108,200
-
lb
|
|
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $29,942 | $13,500 |
$26,115
330,575
kWh
|
$3,827
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4322: Use or replace with energy efficient substitutes | $26,565 | $51,000 |
$5,780
73,162
kWh
|
$847
-
kW-mo/yr
|
$19,938 | - | - | |
| 05 | 2.2113: Repair or replace steam traps | $21,498 | $4,500 | - | - | - |
$21,498
-
MMBtu
|
- | |
| 06 | 2.7496: Install partitions to reduce size of conditioned space | $17,212 | $12,500 | - | - | - |
$17,212
-
MMBtu
|
- | |
| 07 | 2.2511: Insulate bare equipment | $16,394 | $13,060 | - | - | - |
$16,394
-
MMBtu
|
- | |
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $13,127 | $400 |
$11,449
144,929
kWh
|
$1,678
-
kW-mo/yr
|
- | - | - | |
| 09 | 2.1116: Improve combustion control capability | $7,881 | $2,500 | - | - | - |
$7,881
-
MMBtu
|
- | |
| 10 | 2.7224: Reduce space conditioning during non-working hours | $2,915 | $189 |
$2,915
36,899
kWh
|
- | - | - | - | |
| 11 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,485 | $3,600 | - | - | - |
$2,485
-
MMBtu
|
- | |
| 12 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,229 | $500 |
$1,811
22,916
kWh
|
$418
-
kW-mo/yr
|
- | - | - | |
| 13 | 2.7135: Install occupancy sensors | $3,076 | $300 |
$3,076
38,938
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $412,440 | $882,049 |
$356,733
4,515,607
kWh
|
$52,040
-
kW-mo/yr
|
$19,938 |
$(-124,471.0)
-
MMBtu
|
$108,200
-
lb
|
||
| TOTAL IMPLEMENTED | $121,625 | $88,189 |
$46,259
585,565
kWh
|
$6,352
-
kW-mo/yr
|
$19,938 |
$49,076
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs