Assessment Year | 2002 |
---|---|
Principal Product | tools |
NAICS |
n/a
|
SIC | 3423: Hand and Edge Tools, Except Machine Tools and Handsaws |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
92,000
ft2
|
Annual Production | 357,500
pieces
|
Production Hrs. Annual | 2,040
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $97,980 | 893,580 |
kWh
|
$0.11 |
Electricity Demand | $32,018 | 3,900 |
kW-mo/yr
|
$8.21 |
Electricity Fees | $830 | - |
|
- |
Natural Gas | $3,987 | 635 |
MMBtu
|
$6.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $410,128 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $235,910 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | By-product Production Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,025 | $625 |
$4,169
34,849
kWh
|
$1,636
-
kW-mo/yr
|
$(-780.0) | - | - | - | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,530 | $3,825 |
$2,458
20,545
kWh
|
$1,072
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $5,678 | $2,120 |
$3,533
29,534
kWh
|
$2,145
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 4.322: Eliminate old stock and modify inventory control | $14,885 | - | - | - | - | - | - | $14,885 | - | |
05 | 4.214: Purchase appropriately sized material | $216,000 | $3,400 | - | - | - | - | $216,000 | - | - | |
06 | 4.625: Develop standard operating procedures | $159,315 | $6,792 | - | - | - | - | - | - | $159,315 | |
07 | 4.454: Modify startup/shutdown times | $5,695 | $300 | - |
$7,825
-
kW-mo/yr
|
$(-20,250.0) | $18,120 | - | - | - | |
TOTAL RECOMMENDED | $410,128 | $17,062 |
$10,160
84,928
kWh
|
$12,678
-
kW-mo/yr
|
$(-21,030.0) | $18,120 | $216,000 | $14,885 | $159,315 | ||
TOTAL IMPLEMENTED | $235,910 | $4,025 |
$4,169
34,849
kWh
|
$1,636
-
kW-mo/yr
|
$(-780.0) | - | $216,000 | $14,885 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | By-product Production Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs