Assessment Year | 1994 |
---|---|
Principal Product | capacitors and resistors |
NAICS |
n/a
|
SIC | 3675: Electronic Capacitors |
Sales Range | $1 M to 5M |
# of Employees | 95 |
Plant Area |
75,000
ft2
|
Annual Production | 6,500,000
pieces
|
Production Hrs. Annual | 4,290
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $70,740 | 1,417,937 |
kWh
|
$0.050 |
Natural Gas | $15,500 | 3,410 |
MMBtu
|
$4.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,163 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,450 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Liquid (haz) Savings | Gaseous Waste Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.8122: Use tight-fitting lids on material containers to reduce voc emissions | $6,860 | $720 | - | - |
$5,300
-
gal
|
$1,560
-
lb
|
|
02 | 3.8142: Distill contaminated solvents for reuse | $3,603 | $7,080 |
$(-42.0)
(-879)
kWh
|
- |
$3,645
-
gal
|
- | |
03 | 2.2511: Insulate bare equipment | $1,790 | $520 |
$1,790
36,049
kWh
|
- | - | - | |
04 | 2.7261: Install timers and/or thermostats | $1,600 | $150 |
$750
14,947
kWh
|
$850
-
MMBtu
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,270 | $2,070 |
$1,270
25,498
kWh
|
- | - | - | |
06 | 2.4133: Use most efficient type of electric motors | $880 | $1,340 |
$880
17,878
kWh
|
- | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $700 | $300 |
$700
14,068
kWh
|
- | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $460 | $150 |
$460
9,379
kWh
|
- | - | - | |
09 | 3.5248: Separate and recycle scrap metal to foundry or for sale | - | $140 | - | - | - | - | |
TOTAL RECOMMENDED | $17,163 | $12,470 |
$5,808
116,940
kWh
|
$850
-
MMBtu
|
$8,945
-
gal
|
$1,560
-
lb
|
||
TOTAL IMPLEMENTED | $4,450 | $4,000 |
$3,600
72,391
kWh
|
$850
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Liquid (haz) Savings | Gaseous Waste Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs