| Assessment Year | 1994 |
|---|---|
| Principal Product | snowblowing vehicles |
| NAICS |
n/a
|
| SIC | 3711: Motor Vehicles and Passenger Car Bodies |
| Sales Range | $10 M to 50M |
| # of Employees | 170 |
| Plant Area |
65,000
ft2
|
| Annual Production | 30
pieces
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $71,900 | 1,096,424 |
kWh
|
$0.066 |
| Natural Gas | $30,870 | 7,368 |
MMBtu
|
$4.19 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $9,000 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,790 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,660 | $3,200 |
$3,660
55,686
kWh
|
- | - | |
| 02 | 2.7261: Install timers and/or thermostats | $1,960 | $1,050 |
$820
29,894
kWh
|
$1,140
-
MMBtu
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $1,410 | $210 |
$1,410
21,688
kWh
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $790 | $(-290.0) |
$790
12,016
kWh
|
- | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $500 | $150 |
$500
7,620
kWh
|
- | - | |
| 06 | 2.2511: Insulate bare equipment | $380 | $320 | - |
$380
-
MMBtu
|
- | |
| 07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $300 | $100 | - | - | $300 | |
| TOTAL RECOMMENDED | $9,000 | $4,740 |
$7,180
126,904
kWh
|
$1,520
-
MMBtu
|
$300 | ||
| TOTAL IMPLEMENTED | $6,790 | $4,280 |
$5,270
97,596
kWh
|
$1,520
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs