Assessment Year | 2003 |
---|---|
Principal Product | Printed Labels |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
52,000
ft2
|
Annual Production | 31,000
thousand feet
|
Production Hrs. Annual | 4,572
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $75,415 | 1,125,600 |
kWh
|
$0.067 |
Electricity Demand | $27,206 | 3,401 |
kW-mo/yr
|
$8.00 |
Electricity Fees | $5,138 | - |
|
- |
Natural Gas | $5,180 | 699 |
MMBtu
|
$7.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $172,038 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $119,831 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,155 | $30,070 |
$6,601
93,825
kWh
|
$1,602
-
kW-mo/yr
|
- | - | $952 | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $939 | $68 |
$700
9,957
kWh
|
$239
-
kW-mo/yr
|
- | - | - | |
03 | 2.7145: Install skylights | $4,122 | $10,296 | n/a |
$4,122
58,587
kWh
|
- | - | - | - |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,479 | $100 |
$6,456
91,768
kWh
|
$2,023
-
kW-mo/yr
|
- | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $935 | $20 |
$743
10,564
kWh
|
$192
-
kW-mo/yr
|
- | - | - | |
06 | 2.7135: Install occupancy sensors | $697 | $675 |
$697
9,903
kWh
|
- | - | - | - | |
07 | 2.4133: Use most efficient type of electric motors | $43 | $87 |
$33
474
kWh
|
$10
-
kW-mo/yr
|
- | - | - | |
08 | 2.7232: Replace existing hvac unit with high efficiency model | $39,566 | $55,100 | n/a |
$33,077
470,185
kWh
|
$6,489
-
kW-mo/yr
|
- | - | - |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,865 | $10,800 | n/a |
$5,489
78,021
kWh
|
$1,376
-
kW-mo/yr
|
- | - | - |
10 | 2.7229: Air condition only space necessary | $957 | $4,260 |
$957
19,381
kWh
|
- | - | - | - | |
11 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $4,280 | $17,100 | - | - |
$4,280
-
lb
|
- | - | |
12 | 4.521: Clear and rent existing space | $96,000 | $8,340 | - | - | - | $96,000 | - | |
TOTAL RECOMMENDED | $172,038 | $136,916 |
$58,875
842,665
kWh
|
$11,931
-
kW-mo/yr
|
$4,280
-
lb
|
$96,000 | $952 | ||
TOTAL IMPLEMENTED | $119,831 | $55,785 |
$14,533
206,588
kWh
|
$4,066
-
kW-mo/yr
|
$4,280
-
lb
|
$96,000 | $952 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs