Assessment Year | 1993 |
---|---|
Principal Product | Cement |
NAICS |
n/a
|
SIC | 3241: Cement, Hydraulic |
Sales Range | $10 M to 50M |
# of Employees | 83 |
Plant Area |
73,000
ft2
|
Annual Production | 400,000
ton
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $3,280,001 | 75,441,971 |
kWh
|
$0.043 |
Natural Gas | $3,309,407 | 1,663,019 |
MMBtu
|
$1.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $4,201,770 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,374,840 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat | $2,405,000 | $6,313,000 |
$2,405,000
55,318,289
kWh
|
- | - | |
02 | 2.1331: Burn a less expensive grade of fuel | $1,287,000 | $325,000 | - | - | $1,287,000 | |
03 | 2.2428: Use flue gases in radiant heater for space heating, ovens, etc | $332,600 | $250,000 | - |
$332,600
-
MMBtu
|
- | |
04 | 2.7444: Close holes and openings in building such as broken windows | $87,840 | $1,000 | - |
$87,840
-
MMBtu
|
- | |
05 | 2.4133: Use most efficient type of electric motors | $81,180 | $144,120 |
$81,180
1,867,526
kWh
|
- | - | |
06 | 2.4314: Use synthetic lubricant | $6,180 | - |
$6,180
142,145
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,290 | $1,590 |
$1,290
29,601
kWh
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $430 | $960 |
$430
9,965
kWh
|
- | - | |
09 | 2.7261: Install timers and/or thermostats | $250 | $150 |
$190
9,086
kWh
|
$60
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $4,201,770 | $7,035,820 |
$2,494,270
57,376,612
kWh
|
$420,500
-
MMBtu
|
$1,287,000 | ||
TOTAL IMPLEMENTED | $1,374,840 | $326,000 | - |
$87,840
-
MMBtu
|
$1,287,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs