ITAC Assessment: CO0279
ITAC logo
ITAC Assessment: CO0279
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Bottled Soft Drinks
NAICS
n/a
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $1
M
to 5
M
# of Employees 60
Plant Area 74,600
ft2
Annual Production 2,100,000
pieces
Production Hrs. Annual 3,876
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $88,183 1,139,215
kWh
Natural Gas $32,558 8,613
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,220 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,550

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $1,860 $1,960 $1,860
24,033
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,620 $1,780 $1,620
20,809
kWh
-
03 2.4133: Use most efficient type of electric motors $1,270 $2,220 $1,270
16,413
kWh
-
04 2.7261: Install timers and/or thermostats $1,220 $2,850 $90
3,517
kWh
$1,130
-
MMBtu
05 2.7444: Close holes and openings in building such as broken windows $820 $720 - $820
-
MMBtu
06 2.4221: Install compressor air intakes in coolest locations $530 $500 $530
6,741
kWh
-
07 2.2623: Minimize condenser cooling water temperature $410 $240 $410
5,275
kWh
-
08 2.6212: Turn off equipment during breaks, reduce operating time $240 $130 $240
3,224
kWh
-
09 2.2136: Install / repair insulation on steam lines $250 $700 - $250
-
MMBtu
TOTAL RECOMMENDED $8,220 $11,100 $6,020
80,012
kWh
$2,200
-
MMBtu
TOTAL IMPLEMENTED $4,550 $5,160 $3,480
44,842
kWh
$1,070
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs