| Assessment Year | 1993 |
|---|---|
| Principal Product | Computer Parts |
| NAICS |
n/a
|
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 87 |
| Plant Area |
50,000
ft2
|
| Annual Production | 250,000
pieces
|
| Production Hrs. Annual | 4,368
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $105,073 | 1,962,485 |
kWh
|
$0.054 |
| Natural Gas | $6,837 | 1,794 |
MMBtu
|
$3.81 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,220 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,520 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7444: Close holes and openings in building such as broken windows | $920 | $200 |
$20
293
kWh
|
$900
-
MMBtu
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $650 | $180 |
$650
12,016
kWh
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $460 | $600 |
$460
8,499
kWh
|
- | |
| 04 | 2.2437: Recover waste heat from equipment | $590 | $1,100 | - |
$590
-
MMBtu
|
|
| 05 | 2.1332: Convert combustion equipment to burn natural gas | $9,350 | $17,000 |
$9,350
58,910
kWh
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,950 | $3,110 |
$1,950
36,342
kWh
|
- | |
| 07 | 2.7251: Reduce air conditioning load by evaporating water from roof | $1,980 | $9,300 |
$1,980
37,808
kWh
|
- | |
| 08 | 2.4314: Use synthetic lubricant | $320 | $440 |
$320
5,862
kWh
|
- | |
| TOTAL RECOMMENDED | $16,220 | $31,930 |
$14,730
159,730
kWh
|
$1,490
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $3,520 | $3,490 |
$2,620
48,651
kWh
|
$900
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs