ITAC Assessment: CO0249
ITAC logo
ITAC Assessment: CO0249
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product Soft Drinks
NAICS
n/a
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 115
Plant Area 308,000
ft2
Annual Production 6,000,000
pieces
Production Hrs. Annual 2,565
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $129,108 1,852,872
kWh
Natural Gas $50,633 12,754
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,680 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 3.4154: Eliminate leaks in water lines and valves $630 $125 - $630
-
MMBtu
-
02 2.6212: Turn off equipment during breaks, reduce operating time $370 $200 $370
5,275
kWh
- -
03 2.7224: Reduce space conditioning during non-working hours $260 $300 $80
3,224
kWh
$180
-
MMBtu
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,190 $2,840 $2,190
31,360
kWh
- -
05 2.3137: Use power during off-peak periods $960 $2,000 - - $960
06 2.4221: Install compressor air intakes in coolest locations $290 $450 $290
4,103
kWh
- -
07 2.7444: Close holes and openings in building such as broken windows $2,590 $3,000 - $2,590
-
MMBtu
-
08 2.4133: Use most efficient type of electric motors $2,390 $6,430 $2,390
34,291
kWh
- -
TOTAL RECOMMENDED $9,680 $15,345 $5,320
78,253
kWh
$3,400
-
MMBtu
$960
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs