| Assessment Year | 1991 |
|---|---|
| Principal Product | INJECTION MOLDED PLASTIC |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 110 |
| Plant Area |
n/a
|
| Annual Production | 5,000,000
lb
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $232,713 | 4,242,966 |
kWh
|
$0.055 |
| Natural Gas | $11,408 | 2,995 |
MMBtu
|
$3.81 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,378 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,015 | $1,034 |
$2,015
36,635
kWh
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $498 | - |
$352
6,448
kWh
|
- | $146 | |
| 03 | 2.2511: Insulate bare equipment | $8,970 | $10,720 |
$8,970
163,540
kWh
|
- | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $1,060 | $1,810 |
$1,060
19,343
kWh
|
- | - | |
| 05 | 2.7261: Install timers and/or thermostats | $214 | $150 |
$52
2,052
kWh
|
$162
-
MMBtu
|
- | |
| 06 | 2.4133: Use most efficient type of electric motors | $1,271 | $1,972 |
$1,271
23,154
kWh
|
- | - | |
| 07 | 2.7243: Improve air circulation with destratification fans / other methods | $2,350 | $4,000 |
$(-103.0)
(-2,052)
kWh
|
$2,453
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $16,378 | $19,686 |
$13,617
249,120
kWh
|
$2,615
-
MMBtu
|
$146 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs