ITAC Assessment: CO0218
ITAC logo
ITAC Assessment: CO0218
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product ORAL RINSES
NAICS
n/a
SIC 2844: Perfumes, Cosmetics, and Other Toilet Preparations
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area
n/a
Annual Production 970
thousand feet
Production Hrs. Annual 4,290
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,686 1,087,632
kWh
Natural Gas $17,281 4,373
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,434 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,434

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.8121: Apply for tax-free status for energy purchases $1,390 $250 $1,052
-
kWh
$338
-
MMBtu
-
02 3.4115: Recover and reuse cooling water $3,482 - $131
2,638
kWh
- $3,351
03 2.7142: Utilize higher efficiency lamps and/or ballasts $684 $873 $684
13,189
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $230 $380 $230
4,396
kWh
- -
05 2.6232: Install set-back timers $275 $1,200 $95
6,741
kWh
$180
-
MMBtu
-
06 2.7226: Use computer programs to optimize hvac performance $911 $1,000 $527
37,808
kWh
$384
-
MMBtu
-
07 2.4133: Use most efficient type of electric motors $212 $326 $212
4,103
kWh
- -
08 2.4221: Install compressor air intakes in coolest locations $250 $400 $250
4,689
kWh
- -
TOTAL RECOMMENDED $7,434 $4,429 $3,181
73,564
kWh
$902
-
MMBtu
$3,351
TOTAL IMPLEMENTED $7,434 $4,429 $3,181
73,564
kWh
$902
-
MMBtu
$3,351
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs