ITAC Assessment: UD0415
ITAC logo
ITAC Assessment: UD0415
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Bedding materials, filters, cotton/synthetic Textiles
NAICS
n/a
SIC 2297: Non-woven Fabrics
Sales Range $10
M
to 50
M
# of Employees 278
Plant Area 1,089,000
ft2
Annual Production 0
units
Production Hrs. Annual 8,400
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $347,577 6,279,602
kWh
Natural Gas $13,729 2,681
MMBtu
Coal $3,088 276
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $222,680 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,334

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.3191: Use demand controller or load shedder $7,569 - $7,569
-
kWh
-
02 2.4235: Remove or close off unneeded compressed air lines $8,020 $3,000 $8,020
-
kWh
-
03 2.1231: Establish burner maintenance schedule for boilers $200,000 $480,000 - $200,000
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,314 $31,350 $4,314
-
kWh
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,263 $5,400 $1,263
-
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,514 $3,200 $1,514
-
kWh
-
TOTAL RECOMMENDED $222,680 $522,950 $22,680
-
kWh
$200,000
-
MMBtu
TOTAL IMPLEMENTED $12,334 $34,350 $12,334
-
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs