| Assessment Year | 1991 |
|---|---|
| Principal Product | WOOD CABINETS |
| NAICS |
n/a
|
| SIC | 2434: Wood Kitchen Cabinets |
| Sales Range | $10 M to 50M |
| # of Employees | 110 |
| Plant Area |
n/a
|
| Annual Production | 20,000,000
lb
|
| Production Hrs. Annual | 3,445
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $106,169 | 1,885,991 |
kWh
|
$0.056 |
| Natural Gas | $22,762 | 6,060 |
MMBtu
|
$3.76 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,107 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $12,107 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $1,377 | $250 |
$1,140
-
kWh
|
$237
-
MMBtu
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,582 | $2,280 |
$3,582
63,599
kWh
|
- | |
| 03 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,543 | $900 |
$622
11,137
kWh
|
$921
-
MMBtu
|
|
| 04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,955 | $2,000 | - |
$1,955
-
MMBtu
|
|
| 05 | 2.2437: Recover waste heat from equipment | $900 | $1,200 | - |
$900
-
MMBtu
|
|
| 06 | 2.4221: Install compressor air intakes in coolest locations | $500 | $200 |
$500
8,206
kWh
|
- | |
| 07 | 2.7261: Install timers and/or thermostats | $2,035 | $4,200 |
$110
4,396
kWh
|
$1,925
-
MMBtu
|
|
| 08 | 2.4133: Use most efficient type of electric motors | $215 | $685 |
$215
3,810
kWh
|
- | |
| TOTAL RECOMMENDED | $12,107 | $11,715 |
$6,169
91,148
kWh
|
$5,938
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $12,107 | $11,715 |
$6,169
91,148
kWh
|
$5,938
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs