ITAC Assessment: CO0205
ITAC logo
ITAC Assessment: CO0205
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product HOPS OIL FOR BREWERIES
NAICS
n/a
SIC 2076: Vegetable Oil Mills, Except Corn, Cottonseed, and Soybean
Sales Range $10
M
to 50
M
# of Employees 30
Plant Area
n/a
Annual Production 6,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $248,855 4,359,613
kWh
Natural Gas $99,150 25,805
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,071 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.8113: Purchase gas directly from a contract gas supplier $10,700 $6,500 - $10,700
-
MMBtu
02 2.4133: Use most efficient type of electric motors $1,331 $2,240 $1,331
23,447
kWh
-
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $5,600 $500 $5,600
-
kWh
-
04 2.1233: Analyze flue gas for proper air/fuel ratio $4,100 $2,000 - $4,100
-
MMBtu
05 2.4221: Install compressor air intakes in coolest locations $1,600 $400 $1,600
27,257
kWh
-
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,300 $3,100 $1,300
22,274
kWh
-
07 2.7261: Install timers and/or thermostats $440 $300 $100
3,517
kWh
$340
-
MMBtu
TOTAL RECOMMENDED $25,071 $15,040 $9,931
76,495
kWh
$15,140
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs