ITAC Assessment: CO0200
ITAC logo
ITAC Assessment: CO0200
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product BAGS - PAPER & CAN-LIDS
NAICS
n/a
SIC 2674: Uncoated Paper and Multiwall Bags
Sales Range $1
M
to 5
M
# of Employees 15
Plant Area
n/a
Annual Production 42,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $16,863 289,273
kWh
Natural Gas $28,021 7,007
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,260 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,920

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7261: Install timers and/or thermostats $4,200 $2,250 $60
2,345
kWh
$4,140
-
MMBtu
02 2.4133: Use most efficient type of electric motors $420 $280 $420
7,620
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,570 $320 $1,570
27,843
kWh
-
04 2.8121: Apply for tax-free status for energy purchases $1,500 $250 $480
-
kWh
$1,020
-
MMBtu
05 2.2437: Recover waste heat from equipment $950 $2,000 - $950
-
MMBtu
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $580 $990 $580
10,258
kWh
-
07 2.7492: Use proper thickness of insulation on building envelope $540 $1,800 - $540
-
MMBtu
08 2.4221: Install compressor air intakes in coolest locations $500 $700 $500
8,792
kWh
-
TOTAL RECOMMENDED $10,260 $8,590 $3,610
56,858
kWh
$6,650
-
MMBtu
TOTAL IMPLEMENTED $1,920 $530 $900
7,620
kWh
$1,020
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs