Assessment Year | 1990 |
---|---|
Principal Product | CIRCUIT COMPUTER CHIPS |
NAICS |
n/a
|
SIC | 3674: Semiconductors and Related Devices |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
n/a
|
Annual Production | 98,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $187,028 | 4,563,013 |
kWh
|
$0.041 |
Natural Gas | $28,441 | 7,511 |
MMBtu
|
$3.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,160 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,800 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $2,780 | $750 |
$1,950
73,857
kWh
|
$830
-
MMBtu
|
|
02 | 2.7111: Reduce illumination to minimum necessary levels | $4,370 | $13,700 |
$4,370
106,682
kWh
|
- | |
03 | 2.2623: Minimize condenser cooling water temperature | $2,390 | $200 |
$2,390
58,617
kWh
|
- | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,620 | $50 |
$1,620
39,566
kWh
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,010 | $300 |
$1,010
24,619
kWh
|
- | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $790 | $940 |
$790
19,050
kWh
|
- | |
07 | 2.3212: Optimize plant power factor | $6,200 | $7,400 |
$6,200
-
kWh
|
- | |
TOTAL RECOMMENDED | $19,160 | $23,340 |
$18,330
322,391
kWh
|
$830
-
MMBtu
|
||
TOTAL IMPLEMENTED | $7,800 | $1,300 |
$6,970
196,659
kWh
|
$830
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs