| Assessment Year | 1990 |
|---|---|
| Principal Product | CIRCUIT COMPUTER CHIPS |
| NAICS |
n/a
|
| SIC | 3674: Semiconductors and Related Devices |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
n/a
|
| Annual Production | 98,000
pieces
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $187,028 | 4,563,013 |
kWh
|
$0.041 |
| Natural Gas | $28,441 | 7,511 |
MMBtu
|
$3.79 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,160 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,800 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $2,780 | $750 |
$1,950
73,857
kWh
|
$830
-
MMBtu
|
|
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $4,370 | $13,700 |
$4,370
106,682
kWh
|
- | |
| 03 | 2.2623: Minimize condenser cooling water temperature | $2,390 | $200 |
$2,390
58,617
kWh
|
- | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,620 | $50 |
$1,620
39,566
kWh
|
- | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $1,010 | $300 |
$1,010
24,619
kWh
|
- | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $790 | $940 |
$790
19,050
kWh
|
- | |
| 07 | 2.3212: Optimize plant power factor | $6,200 | $7,400 |
$6,200
-
kWh
|
- | |
| TOTAL RECOMMENDED | $19,160 | $23,340 |
$18,330
322,391
kWh
|
$830
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $7,800 | $1,300 |
$6,970
196,659
kWh
|
$830
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs