Assessment Year | 1989 |
---|---|
Principal Product | SCREW MACHINED PRODUCTS |
NAICS |
n/a
|
SIC | 3451: Screw Machine Products |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,030
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $97,185 | 2,110,199 |
kWh
|
$0.046 |
Natural Gas | $6,439 | 1,568 |
MMBtu
|
$4.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,885 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,540 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $6,740 | $6,800 |
$6,740
-
kWh
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,010 | $150 |
$1,010
21,981
kWh
|
- | |
03 | 2.2437: Recover waste heat from equipment | $1,800 | $2,500 | - |
$1,800
-
MMBtu
|
|
04 | 2.7261: Install timers and/or thermostats | $1,345 | $1,000 |
$700
26,964
kWh
|
$645
-
MMBtu
|
|
05 | 2.7245: Use direct air supply to exhaust hoods | $1,200 | $1,900 |
$600
13,189
kWh
|
$600
-
MMBtu
|
|
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $455 | $335 |
$455
10,551
kWh
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $105 | $315 |
$105
2,345
kWh
|
- | |
08 | 2.4221: Install compressor air intakes in coolest locations | $870 | $200 |
$870
19,050
kWh
|
- | |
09 | 2.2511: Insulate bare equipment | $360 | $290 |
$360
7,913
kWh
|
- | |
TOTAL RECOMMENDED | $13,885 | $13,490 |
$10,840
101,993
kWh
|
$3,045
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,540 | $8,090 |
$9,540
61,840
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs