ITAC Assessment: CO0167
ITAC logo
ITAC Assessment: CO0167
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product SCREW MACHINED PRODUCTS
NAICS
n/a
SIC 3451: Screw Machine Products
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 6,030
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $97,185 2,110,199
kWh
Natural Gas $6,439 1,568
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,885 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,540

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.3212: Optimize plant power factor $6,740 $6,800 $6,740
-
kWh
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,010 $150 $1,010
21,981
kWh
-
03 2.2437: Recover waste heat from equipment $1,800 $2,500 - $1,800
-
MMBtu
04 2.7261: Install timers and/or thermostats $1,345 $1,000 $700
26,964
kWh
$645
-
MMBtu
05 2.7245: Use direct air supply to exhaust hoods $1,200 $1,900 $600
13,189
kWh
$600
-
MMBtu
06 2.7142: Utilize higher efficiency lamps and/or ballasts $455 $335 $455
10,551
kWh
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $105 $315 $105
2,345
kWh
-
08 2.4221: Install compressor air intakes in coolest locations $870 $200 $870
19,050
kWh
-
09 2.2511: Insulate bare equipment $360 $290 $360
7,913
kWh
-
TOTAL RECOMMENDED $13,885 $13,490 $10,840
101,993
kWh
$3,045
-
MMBtu
TOTAL IMPLEMENTED $9,540 $8,090 $9,540
61,840
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs