Assessment Year | 1989 |
---|---|
Principal Product | MATERIALS HANDLING EQUIP |
NAICS |
n/a
|
SIC | 3569: General Industrial Machinery and Equipment, Not Elsewhere |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
n/a
|
Annual Production | 20,000
pieces
|
Production Hrs. Annual | 2,574
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $103,097 | 1,740,035 |
kWh
|
$0.059 |
Natural Gas | $31,699 | 7,806 |
MMBtu
|
$4.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,623 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,242 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $1,970 | $250 |
$1,530
-
kWh
|
$440
-
MMBtu
|
|
02 | 2.7244: Revise smoke cleanup from operations | $1,120 | $3,500 |
$680
11,430
kWh
|
$440
-
MMBtu
|
|
03 | 2.6212: Turn off equipment during breaks, reduce operating time | $2,480 | $1,200 |
$1,480
25,205
kWh
|
$1,000
-
MMBtu
|
|
04 | 2.7261: Install timers and/or thermostats | $4,640 | $1,500 |
$1,580
63,599
kWh
|
$3,060
-
MMBtu
|
|
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,240 | $800 |
$1,250
21,102
kWh
|
$990
-
MMBtu
|
|
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $277 | $105 |
$277
4,689
kWh
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $635 | $2,480 |
$635
10,844
kWh
|
- | |
08 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $1,470 | $1,800 |
$1,470
24,912
kWh
|
- | |
09 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,131 | $5,000 |
$3,012
50,996
kWh
|
$(-881.0)
-
MMBtu
|
|
10 | 2.2511: Insulate bare equipment | $660 | $500 |
$660
11,137
kWh
|
- | |
TOTAL RECOMMENDED | $17,623 | $17,135 |
$12,574
223,914
kWh
|
$5,049
-
MMBtu
|
||
TOTAL IMPLEMENTED | $12,242 | $6,335 |
$6,752
125,439
kWh
|
$5,490
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs