Assessment Year | 1988 |
---|---|
Principal Product | SILVER & ZINC BATTERIES |
NAICS |
n/a
|
SIC | 3692: Primary Batteries, Dry and Wet |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
n/a
|
Annual Production | 7,000
pieces
|
Production Hrs. Annual | 2,730
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $74,457 | 1,317,702 |
kWh
|
$0.057 |
Natural Gas | $16,264 | 4,041 |
MMBtu
|
$4.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,674 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,190 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $837 | $1,350 | - |
$837
-
MMBtu
|
- | |
02 | 2.1123: Install automatic stack damper | $906 | $1,100 | - |
$906
-
MMBtu
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $230 | $100 |
$230
4,103
kWh
|
- | - | |
04 | 2.2514: Cover open tanks | $484 | $200 |
$484
8,499
kWh
|
- | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $646 | $650 |
$646
11,430
kWh
|
- | - | |
06 | 3.4115: Recover and reuse cooling water | $6,385 | $8,000 |
$85
1,465
kWh
|
- | $6,300 | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $186 | $218 |
$186
3,224
kWh
|
- | - | |
TOTAL RECOMMENDED | $9,674 | $11,618 |
$1,631
28,721
kWh
|
$1,743
-
MMBtu
|
$6,300 | ||
TOTAL IMPLEMENTED | $9,190 | $11,418 |
$1,147
20,222
kWh
|
$1,743
-
MMBtu
|
$6,300 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs