ITAC Assessment: OK0221
ITAC logo
ITAC Assessment: OK0221
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product CONCRETE AND ASPHALT
NAICS
n/a
SIC 3273: Ready-Mixed Concrete
Sales Range $10
M
to 50
M
# of Employees 275
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 2,600
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $33,076 489,742
kWh
Natural Gas $11,332 2,510
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,178 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,911

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7261: Install timers and/or thermostats $559 $700 - $559
-
MMBtu
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $79 $128 $59
1,465
kWh
- $20
03 2.7142: Utilize higher efficiency lamps and/or ballasts $98 $62 $109
1,758
kWh
$(-11.0)
-
MMBtu
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $270 $10 $270
6,448
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $165 $288 $165
3,517
kWh
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,166 - $1,236
29,308
kWh
- $(-70.0)
07 2.7111: Reduce illumination to minimum necessary levels $162 $100 $162
3,517
kWh
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $412 $344 $412
6,448
kWh
- -
09 2.4131: Size electric motors for peak operating efficiency $267 $100 $267
2,052
kWh
- -
TOTAL RECOMMENDED $3,178 $1,732 $2,680
54,513
kWh
$548
-
MMBtu
$(-50.0)
TOTAL IMPLEMENTED $2,911 $1,632 $2,413
52,461
kWh
$548
-
MMBtu
$(-50.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs