Assessment Year | 1995 |
---|---|
Principal Product | baked goods |
NAICS |
n/a
|
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
80,200
ft2
|
Annual Production | 16,800,000
lb
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $260,901 | 4,923,212 |
kWh
|
$0.053 |
Natural Gas | $34,284 | 7,273 |
MMBtu
|
$4.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,532 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,771 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $14,019 | $250 | - | $14,019 | - | |
02 | 2.4133: Use most efficient type of electric motors | $8,139 | $6,905 |
$8,139
153,576
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $118 | $120 |
$118
2,345
kWh
|
- | - | |
04 | 2.8121: Apply for tax-free status for energy purchases | $1,634 | $250 | - | $1,634 | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $848 | $590 |
$848
14,947
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $458 | $950 |
$458
8,792
kWh
|
- | - | |
07 | 2.6218: Turn off equipment when not in use | $242 | $390 |
$242
4,689
kWh
|
- | - | |
08 | 2.6218: Turn off equipment when not in use | $154 | $760 |
$154
2,931
kWh
|
- | - | |
09 | 3.5311: Recover and reuse waste material | $1,920 | - | - | - | $1,920 | |
TOTAL RECOMMENDED | $27,532 | $10,215 |
$9,959
187,280
kWh
|
$15,653 | $1,920 | ||
TOTAL IMPLEMENTED | $15,771 | $620 |
$118
2,345
kWh
|
$15,653 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs