Assessment Year | 1987 |
---|---|
Principal Product | PRINTED CIRCUIT BOARDS |
NAICS |
n/a
|
SIC | 3672: Printed Circuit Boards |
Sales Range | $1 M to 5M |
# of Employees | 75 |
Plant Area |
n/a
|
Annual Production | 527,000
pieces
|
Production Hrs. Annual | 4,500
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $59,408 | 898,886 |
kWh
|
$0.066 |
Natural Gas | $5,023 | 1,206 |
MMBtu
|
$4.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,233 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,770 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $161 | $200 |
$161
2,345
kWh
|
- | |
02 | 2.2437: Recover waste heat from equipment | $226 | $2,000 | - |
$226
-
MMBtu
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,136 | $700 |
$1,136
17,292
kWh
|
- | |
04 | 2.6212: Turn off equipment during breaks, reduce operating time | $8,463 | $1,200 |
$8,463
128,077
kWh
|
- | |
05 | 2.7261: Install timers and/or thermostats | $1,111 | $1,150 | - |
$1,111
-
MMBtu
|
|
06 | 2.8114: Change rate schedules or other changes in utility service | $3,215 | $250 |
$2,983
-
kWh
|
$232
-
MMBtu
|
|
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $921 | $318 |
$921
14,068
kWh
|
- | |
TOTAL RECOMMENDED | $15,233 | $5,818 |
$13,664
161,782
kWh
|
$1,569
-
MMBtu
|
||
TOTAL IMPLEMENTED | $6,770 | $4,618 |
$5,201
33,705
kWh
|
$1,569
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs