ITAC Assessment: MO0038
ITAC logo
ITAC Assessment: MO0038
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product PENCILS AND PENS
NAICS
n/a
SIC 3951: Pens, Mechanical Pencils, and Parts
Sales Range $10
M
to 50
M
# of Employees 305
Plant Area
n/a
Annual Production 16,800,000
pieces
Production Hrs. Annual 6,120
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $253,305 3,966,002
kWh
Natural Gas $8,123 1,713
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,483 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,449 $357 $1,449
22,567
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $283 $528 $283
4,396
kWh
-
03 2.4221: Install compressor air intakes in coolest locations $2,080 $663 $2,080
32,532
kWh
-
04 2.4312: Improve lubrication practices $1,215 $960 $1,215
19,050
kWh
-
05 2.1311: Replace electrically-operated equipment with fossil fuel equipment $344 - $468
7,327
kWh
$(-124.0)
-
MMBtu
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $112 $320 $112
1,758
kWh
-
TOTAL RECOMMENDED $5,483 $2,828 $5,607
87,630
kWh
$(-124.0)
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs