| Assessment Year | 1987 |
|---|---|
| Principal Product | CONCRETE BLOCK & BRICK |
| NAICS |
n/a
|
| SIC | 3271: Concrete Block and Brick |
| Sales Range | $1 M to 5M |
| # of Employees | 15 |
| Plant Area |
n/a
|
| Annual Production | 2,000,000
pieces
|
| Production Hrs. Annual | 2,184
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $54,072 | 388,042 |
kWh
|
$0.14 |
| Natural Gas | $25,032 | 6,409 |
MMBtu
|
$3.91 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $13,549 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,478 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $324 | $50 |
$324
-
kWh
|
- | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $4,154 | - |
$4,154
-
kWh
|
- | |
| 03 | 2.2511: Insulate bare equipment | $616 | $1,100 | - |
$616
-
MMBtu
|
|
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,705 | $6,000 | - |
$3,705
-
MMBtu
|
|
| 05 | 2.7261: Install timers and/or thermostats | $1,774 | $2,100 | - |
$1,774
-
MMBtu
|
|
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,976 | $5,729 |
$2,976
21,395
kWh
|
- | |
| TOTAL RECOMMENDED | $13,549 | $14,979 |
$7,454
21,395
kWh
|
$6,095
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $4,478 | $50 |
$4,478
-
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs