Assessment Year | 1987 |
---|---|
Principal Product | FILTERS, LUBRICATORS |
NAICS |
n/a
|
SIC | 3567: Industrial Process Furnaces and Ovens |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
n/a
|
Annual Production | 850,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $264,214 | 4,642,145 |
kWh
|
$0.057 |
Natural Gas | $52,945 | 11,837 |
MMBtu
|
$4.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,074 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,107 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $980 | $400 | - |
$980
-
MMBtu
|
|
02 | 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown | $1,316 | $370 |
$489
8,499
kWh
|
$827
-
MMBtu
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,860 | $300 |
$1,860
32,825
kWh
|
- | |
04 | 2.3191: Use demand controller or load shedder | $8,426 | $5,900 |
$8,426
-
kWh
|
- | |
05 | 2.4312: Improve lubrication practices | $2,514 | - |
$2,514
44,256
kWh
|
- | |
06 | 2.4133: Use most efficient type of electric motors | $437 | $1,745 |
$437
7,620
kWh
|
- | |
07 | 2.7261: Install timers and/or thermostats | $1,558 | $800 | - |
$1,558
-
MMBtu
|
|
08 | 2.7226: Use computer programs to optimize hvac performance | $5,303 | $12,500 |
$5,303
93,200
kWh
|
- | |
09 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,417 | $428 |
$202
3,517
kWh
|
$1,215
-
MMBtu
|
|
10 | 2.7492: Use proper thickness of insulation on building envelope | $255 | $520 | - |
$255
-
MMBtu
|
|
11 | 2.7231: Use radiant heater for spot heating | $871 | $4,600 | - |
$871
-
MMBtu
|
|
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,137 | $2,250 |
$6,137
107,855
kWh
|
- | |
TOTAL RECOMMENDED | $31,074 | $29,813 |
$25,368
297,772
kWh
|
$5,706
-
MMBtu
|
||
TOTAL IMPLEMENTED | $15,107 | $18,243 |
$12,079
212,192
kWh
|
$3,028
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs