ITAC Assessment: CO0065
ITAC logo
ITAC Assessment: CO0065
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product PACKAGED BREAD & BUNS
NAICS
n/a
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area
n/a
Annual Production 40,000,000
lb
Production Hrs. Annual 5,200
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $198,523 4,041,618
kWh
Natural Gas $191,979 54,565
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $31,201 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,424

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,628 $300 $2,628
53,634
kWh
-
02 2.4322: Use or replace with energy efficient substitutes $2,367 $800 $2,367
48,359
kWh
-
03 2.4221: Install compressor air intakes in coolest locations $997 $300 $997
20,223
kWh
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $912 $1,200 $912
18,464
kWh
-
05 2.2441: Preheat boiler makeup water with waste process heat $2,772 $7,500 - $2,772
-
MMBtu
06 2.3191: Use demand controller or load shedder $5,124 $3,600 $5,124
-
kWh
-
07 2.7231: Use radiant heater for spot heating $6,995 $6,000 - $6,995
-
MMBtu
08 2.7243: Improve air circulation with destratification fans / other methods $3,715 $3,750 - $3,715
-
MMBtu
09 2.1233: Analyze flue gas for proper air/fuel ratio $697 $300 - $697
-
MMBtu
10 2.7492: Use proper thickness of insulation on building envelope $522 $760 - $522
-
MMBtu
11 2.7261: Install timers and/or thermostats $521 $85 $71
1,465
kWh
$450
-
MMBtu
12 2.7142: Utilize higher efficiency lamps and/or ballasts $3,951 $1,328 $3,951
80,598
kWh
-
TOTAL RECOMMENDED $31,201 $25,923 $16,050
222,743
kWh
$15,151
-
MMBtu
TOTAL IMPLEMENTED $12,424 $6,963 $7,562
154,161
kWh
$4,862
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs