Assessment Year | 1986 |
---|---|
Principal Product | PACKAGED BREAD & BUNS |
NAICS |
n/a
|
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
n/a
|
Annual Production | 40,000,000
lb
|
Production Hrs. Annual | 5,200
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $198,523 | 4,041,618 |
kWh
|
$0.049 |
Natural Gas | $191,979 | 54,565 |
MMBtu
|
$3.52 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,201 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,424 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,628 | $300 |
$2,628
53,634
kWh
|
- | |
02 | 2.4322: Use or replace with energy efficient substitutes | $2,367 | $800 |
$2,367
48,359
kWh
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $997 | $300 |
$997
20,223
kWh
|
- | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $912 | $1,200 |
$912
18,464
kWh
|
- | |
05 | 2.2441: Preheat boiler makeup water with waste process heat | $2,772 | $7,500 | - |
$2,772
-
MMBtu
|
|
06 | 2.3191: Use demand controller or load shedder | $5,124 | $3,600 |
$5,124
-
kWh
|
- | |
07 | 2.7231: Use radiant heater for spot heating | $6,995 | $6,000 | - |
$6,995
-
MMBtu
|
|
08 | 2.7243: Improve air circulation with destratification fans / other methods | $3,715 | $3,750 | - |
$3,715
-
MMBtu
|
|
09 | 2.1233: Analyze flue gas for proper air/fuel ratio | $697 | $300 | - |
$697
-
MMBtu
|
|
10 | 2.7492: Use proper thickness of insulation on building envelope | $522 | $760 | - |
$522
-
MMBtu
|
|
11 | 2.7261: Install timers and/or thermostats | $521 | $85 |
$71
1,465
kWh
|
$450
-
MMBtu
|
|
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,951 | $1,328 |
$3,951
80,598
kWh
|
- | |
TOTAL RECOMMENDED | $31,201 | $25,923 |
$16,050
222,743
kWh
|
$15,151
-
MMBtu
|
||
TOTAL IMPLEMENTED | $12,424 | $6,963 |
$7,562
154,161
kWh
|
$4,862
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs