| Assessment Year | 1986 |
|---|---|
| Principal Product | CANNED & BOTTLED DRINKS |
| NAICS |
n/a
|
| SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
| Sales Range | $5 M to 10M |
| # of Employees | 27 |
| Plant Area |
n/a
|
| Annual Production | 1,200,000
pieces
|
| Production Hrs. Annual | 3,900
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $63,255 | 810,082 |
kWh
|
$0.078 |
| Natural Gas | $42,310 | 8,886 |
MMBtu
|
$4.76 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,613 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $10,551 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7447: Install vinyl strip / high speed / air curtain doors | $5,180 | $675 | - |
$5,180
-
MMBtu
|
|
| 02 | 2.7261: Install timers and/or thermostats | $2,701 | $4,000 | - |
$2,701
-
MMBtu
|
|
| 03 | 2.7492: Use proper thickness of insulation on building envelope | $673 | $3,000 | - |
$673
-
MMBtu
|
|
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,929 | $1,500 |
$2,086
7,620
kWh
|
$(-157.0)
-
MMBtu
|
|
| 05 | 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown | $2,472 | $800 |
$1,920
24,619
kWh
|
$552
-
MMBtu
|
|
| 06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $129 | $300 | - |
$129
-
MMBtu
|
|
| 07 | 2.1222: Install turbulators | $557 | $1,000 | - |
$557
-
MMBtu
|
|
| 08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $556 | $900 |
$556
7,034
kWh
|
- | |
| 09 | 2.4312: Improve lubrication practices | $689 | - |
$689
8,792
kWh
|
- | |
| 10 | 2.2511: Insulate bare equipment | $695 | $620 | - |
$695
-
MMBtu
|
|
| 11 | 2.4221: Install compressor air intakes in coolest locations | $160 | $150 |
$160
2,052
kWh
|
- | |
| 12 | 2.6212: Turn off equipment during breaks, reduce operating time | $419 | $100 |
$419
5,275
kWh
|
- | |
| 13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $453 | $217 |
$453
5,862
kWh
|
- | |
| TOTAL RECOMMENDED | $16,613 | $13,262 |
$6,283
61,254
kWh
|
$10,330
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $10,551 | $8,662 |
$1,302
16,706
kWh
|
$9,249
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs