| Assessment Year | 1986 |
|---|---|
| Principal Product | ICE CREAM |
| NAICS |
n/a
|
| SIC | 2024: Ice Cream and Frozen Desserts |
| Sales Range | $1 M to 5M |
| # of Employees | 54 |
| Plant Area |
n/a
|
| Annual Production | 6,000
Tgal
|
| Production Hrs. Annual | 3,952
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $336,021 | 6,627,491 |
kWh
|
$0.051 |
| Natural Gas | $54,362 | 11,487 |
MMBtu
|
$4.73 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $15,696 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,820 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,900 | $300 |
$2,900
-
kWh
|
- | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,221 | $2,500 |
$2,027
39,859
kWh
|
$(-806.0)
-
MMBtu
|
|
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $763 | $1,500 |
$763
14,947
kWh
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $852 | $300 |
$852
16,706
kWh
|
- | |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $765 | $400 |
$765
14,947
kWh
|
- | |
| 06 | 2.4312: Improve lubrication practices | $3,842 | - |
$3,842
75,909
kWh
|
- | |
| 07 | 2.7492: Use proper thickness of insulation on building envelope | $111 | $250 | - |
$111
-
MMBtu
|
|
| 08 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $73 | $30 |
$73
1,465
kWh
|
- | |
| 09 | 2.2441: Preheat boiler makeup water with waste process heat | $3,902 | $4,000 | - |
$3,902
-
MMBtu
|
|
| 10 | 2.6232: Install set-back timers | $1,267 | $657 |
$1,267
24,912
kWh
|
- | |
| TOTAL RECOMMENDED | $15,696 | $9,937 |
$12,489
188,745
kWh
|
$3,207
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $14,820 | $9,287 |
$11,724
173,798
kWh
|
$3,096
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs