| Assessment Year | 1985 |
|---|---|
| Principal Product | ICE MAKING MACHINES |
| NAICS |
n/a
|
| SIC | 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 210 |
| Plant Area |
n/a
|
| Annual Production | 18,000
pieces
|
| Production Hrs. Annual | 4,420
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $201,290 | 3,660,610 |
kWh
|
$0.055 |
| Natural Gas | $77,896 | 16,468 |
MMBtu
|
$4.73 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $43,139 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $22,010 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $614 | $1,050 |
$614
11,137
kWh
|
- | |
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,488 | $300 | - |
$1,488
-
MMBtu
|
|
| 03 | 2.1222: Install turbulators | $1,131 | $1,000 | - |
$1,131
-
MMBtu
|
|
| 04 | 2.2437: Recover waste heat from equipment | $2,411 | $4,000 | - |
$2,411
-
MMBtu
|
|
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,347 | $200 |
$1,347
24,619
kWh
|
- | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $296 | $250 |
$296
5,275
kWh
|
- | |
| 07 | 2.3132: Recharge batteries on during off-peak demand periods | $3,828 | $2,800 |
$3,828
-
kWh
|
- | |
| 08 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $11,647 | $20,000 |
$15,145
50,703
kWh
|
$(-3,498.0)
-
MMBtu
|
|
| 09 | 2.4312: Improve lubrication practices | $379 | $100 |
$379
7,034
kWh
|
- | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,284 | $2,039 |
$3,284
59,789
kWh
|
- | |
| 11 | 2.8122: Use utility controlled power management | $16,714 | $25,000 |
$16,714
-
kWh
|
- | |
| TOTAL RECOMMENDED | $43,139 | $56,739 |
$41,607
158,557
kWh
|
$1,532
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $22,010 | $28,700 |
$21,609
98,768
kWh
|
$401
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs