Assessment Year | 1985 |
---|---|
Principal Product | BRICKS & CINDER BLOCKS |
NAICS |
n/a
|
SIC | 3271: Concrete Block and Brick |
Sales Range | $5 M to 10M |
# of Employees | 42 |
Plant Area |
n/a
|
Annual Production | 7,000,000
pieces
|
Production Hrs. Annual | 3,172
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $76,441 | 995,018 |
kWh
|
$0.077 |
Natural Gas | $104,510 | 23,109 |
MMBtu
|
$4.52 |
Other Energy | $33,967 | 3,575 |
MMBtu
|
$9.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,756 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,724 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings |
---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,067 | $275 | - |
$4,067
-
MMBtu
|
- | |
02 | 2.1222: Install turbulators | $1,154 | $800 | - |
$1,154
-
MMBtu
|
- | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $4,384 | $10,000 | - |
$4,384
-
MMBtu
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $743 | $150 |
$743
9,672
kWh
|
- | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $398 | $150 |
$398
5,275
kWh
|
- | - | |
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,663 | $1,620 | - |
$3,663
-
MMBtu
|
- | |
07 | 2.7492: Use proper thickness of insulation on building envelope | $512 | $1,799 | - |
$512
-
MMBtu
|
- | |
08 | 2.2136: Install / repair insulation on steam lines | $297 | $295 | - |
$297
-
MMBtu
|
- | |
09 | 2.6212: Turn off equipment during breaks, reduce operating time | $178 | $50 |
$178
2,345
kWh
|
- | - | |
10 | 2.4133: Use most efficient type of electric motors | $1,316 | $50 |
$1,316
17,292
kWh
|
- | - | |
11 | 2.8223: Add air shields to trucks to increase fuel mileage | $1,358 | $100 | - | - |
$1,358
-
MMBtu
|
|
12 | 2.7111: Reduce illumination to minimum necessary levels | $686 | $564 |
$686
9,086
kWh
|
- | - | |
TOTAL RECOMMENDED | $18,756 | $15,853 |
$3,321
43,670
kWh
|
$14,077
-
MMBtu
|
$1,358
-
MMBtu
|
||
TOTAL IMPLEMENTED | $11,724 | $4,953 |
$1,827
24,033
kWh
|
$8,539
-
MMBtu
|
$1,358
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs